How long does the design and planning process take?
Timeframes vary depending on complexity and planning authority workloads, but typically:
- Concept Design: 4–8 weeks
- Pre-Application Determination Period: 5 weeks
- Planning Development & Submission: 4-12 weeks
- Planning Application Determination Period : 8–12 weeks
- Technical Design & Tender: 12–18+ weeks
We’ll provide estimated timescales within our appointment letter.